The Real Estate (Regulation and Development) Act, 2016 (RERA) brought transparency and financial discipline to real estate projects. In Maharashtra, it is administered by MahaRERA. Here is how the key financial requirements work for developers, and where a Chartered Accountant comes in.
Under the Act, a real estate project generally needs to be registered with the state authority before it is advertised, marketed or sold, where the land proposed for development exceeds 500 square metres or the number of apartments exceeds eight, across all phases. Registration involves disclosures about the promoter, the project, approvals, timelines and the project's finances.
Promoters maintain a separate, designated bank account for each registered project. Under the Act, 70% of the amounts realised from allottees are deposited in this account, and the Maharashtra framework can call for a higher share in some situations. The money in the account is used for the cost of land and construction of that project.
Withdrawals from the designated account are made in proportion to the percentage of completion of the project. In Maharashtra, each withdrawal is supported by three certificates:
Form 3 brings the numbers together: the estimated project cost, the cost incurred so far, the collections and the deposits in the designated account. Accurate project books make each certificate quicker and simpler.
The accounts of the project are audited within six months after the end of every financial year by a practising Chartered Accountant. In Maharashtra, the CA's annual report on the statement of accounts is issued in Form 5. It verifies that collections were deposited in the designated account as required and that withdrawals were used for the project. Promoters upload Form 5 on the MahaRERA portal, typically by 30 September each year.
Promoters also update project progress on the MahaRERA portal every quarter, including the construction status and bookings, so that buyers and the authority can track the project.
We support developers with RERA registration, Form 3 certificates, Form 5 annual reports, project accounting, redevelopment accounting and tax, statutory audit and GST. See our real estate services, or visit the MahaRERA website for the official rules and circulars.
Form 3 is a certificate from a practising Chartered Accountant certifying the cost incurred on the project and the amount eligible for withdrawal from the designated RERA account in Maharashtra.
Form 5 is the Chartered Accountant's annual report on the statement of accounts of a registered project in Maharashtra, confirming that collections and withdrawals followed the rules.
Under the Act, 70% of the amounts realised from allottees are deposited in the designated account and used for the cost of land and construction of that project.
This article is general information as at 4 November 2026. Laws, rates and due dates change, so confirm the position for your situation before acting.